Schools receiving their HR and/or Payroll service from Carlisle will transfer to iTrent effective from 1 December 2017. The key dates for the project are detailed in the table below;

Date

Activity

July - August 2017

iTrent design and build

September 2017

User Acceptance Testing

October 2017

Parallel Run 1

November 2017

Parallel Run 2

1 December 2017

Itrent Go Live for Carlisle

December 2017 – January 2018

More intensive project support available for schools adapting to iTrent

 

Schools receiving their HR and/or Payroll service from Sheffield will transfer to iTrent effective from 1 March 2018. The key dates for the project are detailed in the table below;

Date

Activity

July - August 2017

iTrent design and build

September - November 2017

User Acceptance Testing, System Preparation and Reporting build

December 2017

Final User Acceptance Testing before parallel running

January 2018

Parallel Run 1 for Sheffield

February 2018

Parallel Run 2 for Sheffield

1 March 2018

iTrent Go Live for Sheffield

 

Schools receiving their HR and/or Payroll service from Sittingbourne will transfer to iTrent effective from 1 March 2018. The key dates for the project are detailed in the table below;

Date

Activity

July - August 2017

iTrent design and build

September - November 2017

User Acceptance Testing, System Preparation and Reporting build

December 2017

Final User Acceptance Testing before parallel running

January 2018

Parallel Run 1 for Sittingbourne

February 2018

Parallel Run 2 for Sittingbourne

1 March 2018

iTrent Go Live for Sittingbourne